$113.1M obligated to convert a Hagerstown building ICE already owns
A same-day sibling of the Arizona renovation order, the Hagerstown task order carries a $641.8 million potential value against a funded period that ends October 31, 2026. Four modifications have been recorded without a single additional dollar obligated.
- Current award
- $113.1M
- Award ID (PIID)
- 70CDCR26FR0000035
- Last verified
- August 20, 2026
Share with the sourcing attached
Both copied strings carry the attribution language and the canonical link, and label the reported extension figure as reported potential value rather than obligated spending.
The receipt
ICE ordered KVG LLC to convert an agency-owned building in Hagerstown, Maryland into a detention and processing facility, committing about $113.1 million at signing on March 6, 2026. Four later actions changed the order without adding money. About $15.6 million had been paid out at the cutoff.
Contract scope as written on the federal record: “Renovation of an existing, ICE-owned permanent structure in Hagerstown, Maryland to serve as a processing and detention facility, with wraparound services.”
The chain
- 01
Public money
ICE custody operations appropriations
Detention operations are funded from ICE custody operations accounts, expanded by P.L. 119-21.
No source attached - 02
Award
PIID 70CDCR26FR0000035
Delivery order signed March 6, 2026 under a Navy indefinite-delivery vehicle, issued by ICE Detention Compliance and Removals.
No source attached - 03
Contractor
KVG LLC
Recipient of record and its own listed parent recipient; the record reports no corporate parent above it. Sources outside the award record — the Army award announcement, a Court of Federal Claims opinion and GAO — establish that the company was contracted to construct, operate and maintain the site through April 17, 2026.
No source attached - 04
Facility
No facility identified
The record describes a structure in Hagerstown, Maryland. It names no facility and no matching row exists in the ICE detention workbook this project carries.
No source attached - 05
Evidence boundary
Documented in the same detention system. Not presented as a causal attribution. The record below is documented alongside this funding chain, not asserted to be caused by it.
Human cost
Not established by this record
The contract record documents money, scope and dates. It documents no conditions, no treatment and no outcome for anyone held.
No source attached
Contract timeline
March 6, 2026
Step 01
Award signed
$113,052,115.78Description as recorded: “THIS TASK ORDER IS TO PROCURE THE RENOVATION OF EXISTING, ICE-OWNED PERMANENT STRUCTURE IN HAGERSTOWN, MD TO SERVE AS A PROCESSING AND DETENTION FACILITY AND PROVIDE ALL NECESSA…”
April 2, 2026
Step 02
Modification P00001 — other administrative action
Description as recorded: “THIS TASK ORDER IS TO PROCURE THE RENOVATION OF EXISTING, ICE-OWNED PERMANENT STRUCTURE IN HAGERSTOWN, MD TO SERVE AS A PROCESSING AND DETENTION FACILITY. THIS MODIFICATION IMPL…”
May 18, 2026
Step 03
Modification P00002 — other administrative action
Description as recorded: “THIS TASK ORDER IS FOR THE RENOVATION OF EXISTING, ICE-OWNED PERMANENT STRUCTURE IN HAGERSTOWN, MD. THIS MODIFICATION PARTIALLY LIFTS THE STOP WORK ORDER.”
June 18, 2026
Step 04
Modification P00003 — change order
Description as recorded: “THIS TASK ORDER IS FOR THE RENOVATION OF EXISTING, ICE-OWNED PERMANENT STRUCTURE IN HAGERSTOWN, MD AND FULL DETENTION SERVICES. MODIFICATION P00003 INCORPORATES AN UPDATED PWS I…”
July 31, 2026
Step 05
Modification P00004 — supplemental agreement for work within scope
Description as recorded: “THIS TASK ORDER IS FOR THE RENOVATION OF EXISTING, ICE-OWNED PERMANENT STRUCTURE IN HAGERSTOWN, MD AND FULL DETENTION SERVICES. MODIFICATION P00004 EXTENDS THE PERIOD OF PERFORM…”
October 31, 2026
Step 06
Current period of performance ends
End of the currently funded ordering period on the federal record. It is not a closeout date and it does not establish that work stopped.
March 5, 2029
Step 07
Potential period ends if every option is exercised
Latest end date reachable under the award if the government exercises all remaining options. The record does not establish that it will.
Period of performance: March 6, 2026 to October 31, 2026, with a potential end of March 5, 2029 if options are exercised.
Award trajectory
How the obligation on this award moved, action by action, against the value ceilings the source reports.
- Cumulative reported obligation
- Potential value (all options) — $641,795,971.68
- Current value (exercised options) — $113,052,115.78
- Cash outlayed to date, as of 2026-08-20 — $15,612,687.83
Source: USAspending.gov award 70CDCR26FR0000035, retrieved 2026-08-20. Unit: US dollars, nominal, not inflation-adjusted.
The line steps only on dates the source records. Cash outlay is reported as a single to-date total with no action-level dates, so it is drawn as one marker at the retrieval date and never as a line across time. Each action mark is keyboard focusable.
Contract actions as a table (5) — select a modification for its evidence trace
| Action date | Mod | Action | This action | Cumulative obligation |
|---|---|---|---|---|
| Mar 06, 2026 | DELIVERY ORDER | $113,052,115.78 | $113,052,115.78 | |
| Apr 02, 2026 | OTHER ADMINISTRATIVE ACTION | $0.00 | $113,052,115.78 | |
| May 18, 2026 | OTHER ADMINISTRATIVE ACTION | $0.00 | $113,052,115.78 | |
| Jun 18, 2026 | CHANGE ORDER | $0.00 | $113,052,115.78 | |
| Jul 31, 2026 | SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | $0.00 | $113,052,115.78 |
Contractor and facilities
Recipient
KVG
KVG LLC
Holds the task order to renovate an ICE-owned structure in Hagerstown, Maryland for use as a processing and detention facility. The record reports no corporate parent above it.
Contractor profileThe facility record beside the money record
Evidence boundary
What the evidence establishes
- ICE obligated about $113.1 million on March 6, 2026, and no recorded action since has changed that figure.
- A June 18, 2026 change order and a July 31, 2026 supplemental agreement were recorded within the existing scope.
- Potential value is about $641.8 million against a potential period running to March 5, 2029.
- The currently funded period ends October 31, 2026.
What it does not establish
- It does not establish what the June 2026 change order changed.
- It does not establish that the renovated structure opened, that it holds anyone, or who would run it.
- It does not establish any relationship between this order and the Surprise, Arizona order beyond the shared signing date and near-identical scope language.
- It does not establish that ICE will fund the order beyond October 31, 2026.
Human impact linkage
No harm record can attach to this award. The record does not establish that anyone has been held at this location.
How this project categorizes harmOversight and intervention windows
These records live in the central leverage ledger. A date passing never closes one; it flags it for review.
No intervention window is recorded for this receipt in sources currently indexed.
Institutional channels · not windows
Standing official routes. Each establishes only that the channel exists; none implies a request, complaint, hearing, or investigation, and none carries a status or a date.
No official channel is published for this case.
Source docket
Provenance and corrections
- Source snapshot
- August 20, 2026
- Parser state
- automated parse manually reviewed
- Claim status
- verified against source
- Corrections
- None recorded